What is the first step in the sequence of operations for a natural draft gas fired boiler?

Prepare for the 5th Class Power Engineering Exam with comprehensive flashcards and multiple-choice questions. Each question includes hints and explanations. Get exam-ready!

In the operation of a natural draft gas-fired boiler, initiating the startup process is a crucial first step. The operating control plays an essential role in this phase by ensuring that all systems are in the correct state for safe and efficient operation. When the operating control initiates a startup, it triggers the necessary sequence of events to prepare the boiler for ignition and operation.

This includes checking safety interlocks, preparing the ignition system, and ensuring that fuel gas is available. Once the startup sequence has been initiated correctly, it allows for the subsequent steps to occur in an orderly fashion, such as energizing the ignition transformer and igniting the main burner.

By ensuring that this first step occurs correctly, the risk of issues during ignition is minimized, thereby promoting safe and reliable boiler operation. The sequencing is critical because it assures that each component is functioning properly before moving on to ignite the fuel, making it a foundational aspect of the boiler's startup procedure.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy